The goal
An investor wanted to add rental income across a portfolio of single-family properties without managing five separate construction projects.
How we built it
We started with feasibility reviews of every property, confirming setbacks, fire access and utility capacity. Two standardized plans covered all ten units, which simplified plan check and let us buy materials and schedule trades as one program.
Construction was staggered so framing, MEP and finish trades rolled from site to site without downtime.
The result
All ten units were delivered in three phases, and each phase was leased while the next was finishing.