The goal
A build-to-rent developer needed a reliable schedule and lender-ready reporting for a 32-unit garden community.
How we’re building it
We procured switchgear and windows during permitting to protect the schedule, and phased the buildings so the first can be leased while the second is completed. Monthly cost-to-complete reports keep the developer and lender aligned.
Status
Building A is framed and in rough-in. Building B foundations are complete.